The test house has returned the electromagnetic compatibility report. The injector passed. At the release review, someone opens the standards register and spots an amendment issued after the test plan was agreed. The project manager wants to know whether to book another week in the laboratory.
I’d ask the electronics engineer to bring the circuit diagram and the original test protocol to that meeting. In this hypothetical case, the injector uses a Hall-effect sensor to determine plunger position. If an external magnetic field could make a partly travelled plunger look as though it had reached the end of its stroke, the device might tell the patient that an incomplete injection had finished. That is a good reason to look closely at what the laboratory actually measured.
What changed for this product?
Take a real historical amendment. In 2020, Amendment 1 to IEC 60601-1-2 introduced subclause 8.11 on immunity to nearby magnetic fields. It gives manufacturers a route through component sensitivity, physical separation and exposure risk, as well as a route directly to testing. For a handheld injector, the sensor’s position inside its enclosure and the sources it could approach during intended use matter. A drawing, the layout of an attached accessory and the use scenario are all relevant evidence. IEC amendment
There is a separate question for regulatory affairs. Which market and which conformity claim are under review? For a US submission, FDA lists edition 4.1 under recognition 19-36 and specifies two exclusions. For the EU, MDR Article 8 links presumption of conformity to the requirements covered by a cited harmonised standard. Article 10(9) calls for timely consideration of changes to harmonised standards used to declare conformity. The team needs the applicable reference, its scope and any transition arrangements for the market in question. FDA recognition record · EU MDR
For this example, assume the team is preparing a US submission against edition 4.1. The earlier laboratory report covers edition 4.0. Its pass result is still evidence for the configurations and disturbances actually tested. Now we can give the laboratory a narrower question.
A one-page impact assessment
The following is an illustrative completed record for the magnetic-field issue. The team tracks the amendment’s other changes separately before making an edition-wide conformity claim.
| Decision point | Evidence and conclusion |
|---|---|
| Baseline and change | US submission. Board C, firmware 2.4, EMC report R17 against edition 4.0. The report contains no exposure or monitoring that answers subclause 8.11. |
| Applicability | A Hall-effect sensor sits near an accessible surface. The enclosure does not ensure 150 mm separation. The exposure review cannot justify accepting the risk for the intended home use. |
| Potential failure | A false end-of-stroke indication could lead the patient to believe a partial dose was complete. A power-on check would miss this failure. |
| Additional evidence | The verification lead commissioned the applicable proximity-field tests during delivery. The laboratory measured delivered quantity independently of the sensor and recorded every completion indication against the approved limits. |
| Disposition | In this example, report R24 records that all applicable exposures met the delivery limits and produced no false completion. The design lead accepts R17 and R24 together for this issue. Regulatory affairs checks the full amendment assessment before release. |
I would sign this conclusion. “R17 covers the original EMC exposures. R24 addresses the proximity-field gap for board C and firmware 2.4 during delivery. Both support this configuration.” If R24 had shown a false completion, I would reopen the design and the risk assessment before deciding what to retest.
If we went back to the laboratory tomorrow, what could we learn that would change our release decision? Write that into the protocol. It makes for a better test and a much easier conversation about the booking.