Your test report is approved. The results pass. The requirements document is controlled.
Six months later, someone asks which requirements the software was verified against.
The report references “the current version”.
Current when? When the protocol was written, when testing started, when the report was approved—or when somebody opens the link today?
This small ambiguity can undermine an otherwise sound body of development evidence. The testing may have been performed correctly, but reconstructing what it demonstrated now depends on detective work.
In the recent article “Does IEC 62304 Really Require Unit Testing?”, we considered how teams justify their verification methods. There is an equally practical question behind that discussion: can we identify exactly what those methods were applied to?
“Current” describes a moving target
A reference to the current version can be useful when directing somebody to the procedure they should follow today. Historical evidence serves a different purpose.
A verification report records an activity performed against particular acceptance criteria, using a particular product configuration. Its meaning should remain understandable after the project has moved on.
Consider an illustrative software release:
| Evidence item | Configuration used |
|---|---|
| Software requirements | SRS-014, revision 3 |
| Software tested | Release 2.4.0, build 1842 |
| Test protocol | TP-027, revision 2 |
| Approved test report | TR-027, revision 1 |
The report concludes that the tested software meets the requirements covered by the protocol.
Later, SRS-014 advances to revision 4. A requirement now specifies that a communication-loss warning must appear within five seconds, rather than ten.
The original report still records what happened. However, passing a ten-second acceptance criterion does not, by itself, establish compliance with a five-second criterion.
If its reference simply says “current version”, a reader could mistakenly interpret the report as evidence against revision 4.
Two workable ways to preserve the connection
The first approach is straightforward: identify the document and its revision explicitly.
The report references SRS-014 revision 3 and TP-027 revision 2, alongside the exact software build and relevant hardware, settings and test environment. The referenced records remain retrievable.
This is often sufficient for a smaller project. It is visible, understandable and easy to review.
The second approach is to reference a uniquely identified controlled baseline.
For example, the report identifies verification baseline VB-2.4-01. Its controlled manifest records the requirements revision, protocol revision, software build and other relevant configuration items.
The report need not repeat every revision if that baseline reference reliably resolves to the exact configuration used. Where configurations differ between test runs, the records should preserve those differences.
The essential condition is that the baseline’s historical contents remain reconstructable. A folder called “Latest approved documents”, or a link that always opens the newest revision, does not provide that assurance.
Both approaches can work together: explicit references for key items, supported by a baseline for the wider configuration.
Revision 4 does not mean revising everything
A common concern is that explicit references create an endless chain of document updates.
That happens when reference maintenance is confused with change assessment.
An approved report should continue to identify what was actually tested. Replacing “revision 3” with “revision 4” merely to make the reference look current risks misrepresenting the evidence.
Instead, assess the change and record the decision.
A spelling correction may have no effect on requirements meaning, implementation or verification coverage. A changed timing limit, interface behaviour or risk control may affect all three.
For the communication-loss example, the assessment should consider whether the existing raw results and test conditions already demonstrate the tighter limit. If they do, a documented evaluation may support reuse. If they do not, further verification is needed. Any software modification also calls for consideration of affected functions and appropriate regression testing.
The outcome might be a change assessment, supplementary report, updated traceability record or new verification activity, following the organisation’s procedures. It need not be a wholesale revision of every document containing a reference.
Connect the evidence to the released product
The same discipline applies between the tested build and the released software.
FDA’s Content of Premarket Submissions for Device Software Functions, issued on 14 June 2023, recommends documenting tested software versions and describing differences between the tested and released versions, with an assessment of their potential effects on safety and effectiveness. These are submission recommendations, rather than a prescription for one particular referencing format.
The practical engineering principle is simple: preserve the original evidence, identify subsequent changes and explain why the evidence remains applicable—or what additional work is needed.
A useful review question is therefore:
Could someone outside the project reconstruct the requirements, product configuration and verification evidence supporting this release without asking the original team?
If the answer depends on what “current” meant at the time, there is probably a small configuration-management improvement worth making.